TECHNICAL PUBLICATION · DIGITAL ENGINEERING · DISTRIBUTED ENERGY

Digital Twins for Distributed Energy: From Zero Export to Grid-Integrated Solar and Storage

E03 is a simulation-based engineering case study exploring how rooftop photovoltaics, battery energy storage, digital monitoring and grid-export controls can be coordinated for 226 residential users in Ayaviri, Peru.

Scope: engineering and financial scenario assessment—not a commissioned installation or an approved grid-connection study.

Explore the E03 results

Leer esta publicación en español →

01 · CONCEPT AND METHODOLOGY

What a digital twin contributes to distribution networks

A digital twin links an engineering representation of the physical network with relevant operational data. It supports the study of interactions among household demand, photovoltaic generation, battery storage, advanced metering infrastructure (AMI) and network operating limits. In E03, this approach is used primarily as a simulation and decision-support prototype; continuous field synchronization has not yet been demonstrated for all users.

Six-stage engineering workflow

1. CharacterizationIdentify consumers, electrical demand, grid assets and initial operating conditions.
2. Digital representationConstruct a model of the distribution network and its distributed energy resources.
3. SimulationAssess power flows, voltages, generation profiles, demand and storage operation.
4. Scenario evaluationCompare Zero Export with potential future compensation mechanisms, subject to applicable regulation.
5. Economic assessmentEstimate investment, operating costs, savings, financial returns and sensitivities.
6. Progressive scalingUse validated results to guide subsequent technical and geographical expansion.

This application-oriented sequence complements CONSCOSA's broader R-E-C-P-G-A methodology for digital twins in infrastructure.

02 · SYSTEM ARCHITECTURE

Connecting distribution assets, distributed resources and information

01 · ELECTRICAL NETWORKGrid model

Transformers, feeders, residential customers, demand profiles and electrical operating conditions.

02 · DISTRIBUTED RESOURCESPV and BESS

Solar generation, direct self-consumption, battery dispatch, surplus management and export controls.

03 · INFORMATIONAMI and cloud

Metering architecture, data exchange, scenario updates and operating analytics.

Reference location: Ayaviri, Puno, in the Electro Puno concession area. The engineering model uses a typical network similar to SED 6001050; its electrical hosting capacity has not been confirmed through a validated connection study.

Functional architecture of the E03 digital twin

Conceptual architecture only. Physical PV–BESS/network power exchange and AMI/control information exchange can be bidirectional. Arrows show conceptual relationships; dashed green lines represent planned data exchange without specifying a flow direction or validated dispatch. The reference SED, communications and field interfaces require verification.

Reference equipment and constraints

ParameterE03 referenceEngineering qualification
PV per household1.44 kWpModeled as two 720 Wp modules; commercial specifications and inverter compatibility require verification.
BESS per household1.024 kWh nominal0.80 kW reference battery/inverter power per household; usable capacity depends on operating constraints.
Aggregated BESS power180.80 kWReference equipment sum, not guaranteed network support capability.
Smart meteringAMI conceptField deployment and individual measured profiles have not been demonstrated.
Cloud communication15-minute intervalCommunication requirement, not evidence of individual meter sampling frequency.
03 · REFERENCE CONFIGURATION

The E03 reference configuration

The original E03 model combines distributed photovoltaic systems and lithium battery storage. Its investment estimate includes equipment and a provision for complementary import-related logistics and contingencies.

Residential users226Reference pilot population
Installed solar PV325.44 kWp1.44 kWp per household
Battery storage231.424 kWh1.024 kWh nominal per household
CapExPEN 892,665.65E03 reference investment
Annual modeled demand113.74 MWhAggregate reference load
Financial horizon20 yearsScenario evaluation period
04 · OPERATING STRATEGY

From a digital model to a grid-aware operating strategy

The engineering approach combines load and solar profiles, battery state-of-charge constraints, energy exchanges and configurable export ceilings. The reference deployment concept begins with Zero Export operation and evaluates a hypothetical transition to Net Billing from year three. Net Metering is also considered as a comparative compensation scenario.

Cloud communication: the project specifies a 15-minute cloud communication interval. This is a communications constraint and must not be confused with proof that all 226 homes already have individually measured quarter-hourly data. The simulation's time step and the provenance of input profiles must be documented separately.

Regulatory distinction. Zero Export, Net Billing and Net Metering are modeled operating or compensation cases. Their inclusion does not imply that a particular compensation mechanism or injection capacity has been approved for this location.
05 · E03 ANNUAL ENERGY BALANCE

Understanding modeled generation, demand and surplus

The reference scenario includes a 20% demand adjustment applied to historical consumption profiles. The following figures reproduce the annual E03 model balance reported in the Spanish technical publication.

Annual PV generation701.62 MWhSimulated annual output
Direct PV consumption69.25 MWhPV supplied directly to loads
Battery discharge44.48 MWhEnergy supplied by storage

E03 annual results · two complementary accounting views

A · How household demand is served

Direct photovoltaic use69.25 MWh
Battery discharge44.48 MWh
Modeled annual demand113.74 MWh

These demand-side figures sum within rounding. Aggregate grid imports are modeled as zero; this is not a verified individual-household outcome.

B · Photovoltaic generation and potential surplus

Annual PV generation701.62 MWh
Reference potential surplus583.08 MWh

Separate model indicators, not a closed generation allocation. Battery charging, losses, curtailment and operating boundaries require reconciliation before a complete Sankey diagram is published.

Operating distinction: the 583.08 MWh potential surplus is not physical grid injection under Zero Export. The 100 kW export-ceiling study is a separate sensitivity scenario and must not be conflated with the unconstrained reference case.
Annual indicatorModel resultInterpretation
Electricity demand113,736.53 kWhReference annual consumption, including the modeled 20% adjustment.
Photovoltaic generation701,617.19 kWhSimulated annual PV production.
Direct photovoltaic consumption69,253.58 kWhPV used directly by consumers.
BESS discharge44,482.95 kWhEnergy supplied by battery storage.
Grid imports0.00 kWhAggregate reference model output; not a verified household-level operating outcome.
Modeled energy surplus583,081.28 kWhPotential export reference before operational injection restrictions.
Zero Export interpretation: modeled surplus does not constitute physical grid injection during the first two years. The actual Zero Export controller, inverter limitations and curtailment must be verified independently.
06 · NETWORK CONSTRAINTS

Export limits and energy curtailment

In an exploratory aggregate simulation, a hypothetical 100 kW export ceiling produces markedly different solar curtailment depending on installed PV capacity. The ceiling is a sensitivity parameter, not an Electro Puno connection authorization.

Effect of a hypothetical 100 kW export ceiling

0.72 kWp + BESS
7.34 MWh
1.44 kWp + BESS
265.31 MWh

Illustrative annual solar curtailment in the aggregate model, not an approved grid export limit. Bars are scaled to the largest displayed curtailment value.

PV per householdBESS per householdAnnual exportSolar curtailment
0.72 kWpNone275.40 MWh7.34 MWh
0.72 kWp1.024 kWh224.82 MWh7.34 MWh
1.44 kWpNone363.98 MWh268.39 MWh
1.44 kWp1.024 kWh317.79 MWh265.31 MWh

These figures are preliminary model outputs. They illustrate why grid hosting capacity and curtailment must be incorporated into project sizing, rather than maximizing installed solar capacity in isolation.

07 · NIGHTTIME AUTONOMY

Nighttime autonomy: an engineering constraint

Modeled electricity demand from 18:00 to 06:00 represents approximately 38.16% of annual demand. The E03 reference battery capacity is 1.024 kWh nominal per household, but usable energy depends on state of charge, operating limits, conversion efficiency and individual load profiles.

An aggregate energy-to-average-load calculation can provide an illustrative equivalent duration; it is not a guaranteed number of backup hours for an individual household. A bankable design requires household-level nighttime profiles, battery dispatch and reliability criteria.

08 · FINANCIAL EVALUATION

Transition from Zero Export to hypothetical Net Billing

The original E03 financial model considers two initial years without recognized export revenue. From year three onward, it simulates Net Billing compensation for eligible surplus energy. This is an evaluation assumption, not an approved tariff or connection arrangement.

Financial indicatorE03 resultInterpretation
Assumed export pricePEN 0.3029/kWhModel assumption; not an authorized export tariff.
Avoided purchase pricePEN 0.70/kWhAssumed retail energy cost.
Unrestricted reference annual export valuationPEN 176,615.32Before annual degradation and the initial Zero Export period.
Year 1 · Zero ExportPEN 0.00 export revenueNo modeled export compensation.
Year 2 · Zero ExportPEN 0.00 export revenueNo modeled export compensation.
Year 3 · projected export577,265.04 kWhHypothetically eligible energy under the model.
Year 3 · projected export revenuePEN 174,853.58Conditional simulated revenue.

Reference scenario · operating and revenue timeline

Year 1Zero ExportExport revenue PEN 0
Year 2Zero ExportExport revenue PEN 0
Years 3–20Hypothetical Net BillingYear 3 modeled export revenue PEN 174,853.58

Scenario assumptions, not approved compensation arrangements. Future export revenue depends on technical hosting capacity, regulation, operating restrictions and PV degradation.

Financial viability of the reference scenario

Financial net present value (NPV / VAN)PEN 740,722.78Positive under the reference assumptions
Financial benefit–cost ratio1.5352Model result
CapExPEN 892,665.65Initial reference investment

Net present value · three evaluation perspectives

Financial NPV
PEN 740,722.78
Social NPV
PEN 1,581,219.29
Multi-actor NPV
PEN 1,563,504.30

All figures are expressed in Peruvian soles (PEN). These indicators reflect different assessment perspectives and must not be added or interpreted as equivalent cash flows. Results remain conditional on the E03 model assumptions.

Additional financial parameterReference valueScope
Evaluation horizon / discount rate20 years / 8% annuallyReference financial model.
Social NPV / multi-actor NPVPEN 1,581,219.29 / PEN 1,563,504.30Distinct perspectives; not interchangeable with financial NPV.
Initial operating strategyZero Export in years 1–2Modeled scenario.
Hypothetical compensationNet Billing from year 3Subject to applicable regulation and grid feasibility.

The reference cash flow includes self-consumption savings, simulated export revenue from year three, operating and maintenance expenses, PV degradation, and scheduled battery and inverter replacements. Its NPV assumes the modeled energy surplus can be compensated without the actual network export limits used in subsequent sensitivity analyses.

Financial caution: a preliminary export peak of approximately 255.52 kW requires independent verification against hosting capacity, voltage, thermal constraints, reverse power flow and protection settings. Export restrictions, prolonged Zero Export or fewer participating households can materially change the NPV. The positive reference NPV is not an investment guarantee.
09 · COMMERCIAL FEASIBILITY

Equipment and commercial feasibility of alternative scenarios

Exploratory comparisons show that the economically preferred PV–BESS configuration changes with the compensation scheme and permitted export capacity. Removing storage can improve modeled financial returns when backup and grid-support benefits are not remunerated; this does not eliminate its potential technical value.

The E03 reference CapEx is PEN 892,665.65. Alternative CapEx and net-present-value results are sensitivity estimates derived from documented budget prices and simplifying scaling assumptions—not supplier quotations or investment guarantees.

Equipment realism. Fractional battery capacities such as 0.256 kWh and hypothetical 0.24 kWp household PV systems are not treated as verified commercial configurations. Practical alternatives must use complete, compatible modules and be checked against manufacturer specifications.
10 · VALIDATION ROADMAP

Engineering validation roadmap

  1. Validate input data: establish the source and representativeness of each household's demand and solar profiles.
  2. Confirm equipment: verify module, inverter, storage and export-controller compatibility using actual supplier specifications.
  3. Assess hosting capacity: conduct power-flow, voltage, thermal and reverse-power studies for the relevant distribution assets.
  4. Test autonomy: simulate household-level state of charge and nighttime service, including outages where backup is required.
  5. Reassess economics: update CapEx, replacement schedules, operational expenditure and compensation assumptions.
  6. Move toward deployment: connect field measurements, communications and operating controls to the digital twin.

CONSCOSA's approach is to use digital twins as decision-support systems connecting technical design, grid constraints, economic assessment and implementation planning.